Original Cost
₹1878 Cr
Baseline estimate
Revised Cost
₹2459 Cr
Latest approved cost
Expenditure
₹2764 Cr
Spent to date
Utilization
112.4%
Of revised budget
Cost Status
+30.9%
+₹581 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹2764 Cr
Remaining
₹0 Cr
Total
₹2459 Cr
Original Cost
₹1878 Cr
Revised Cost
₹2459 Cr
Increase
+₹581 Cr
Escalation
+30.9%
Project Approved
Construction / Implementation
Original End Date
31/12/2024
Revised Completion
31/03/2026
Completed
Cost has increased by ₹581 Cr (30.9%) from the original estimate of ₹1878 Cr.
Expenditure stands at ₹2764 Cr, which is 112.4% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.