Hotgi-Kudgi-Gadag Doubling Project
Original Cost
₹1878 Cr
Baseline estimate
Revised Cost
₹2459 Cr
Latest approved cost
Expenditure
₹2764 Cr
Spent to date
Utilization
112.4%
Of revised budget
Cost Status
+30.9%
+₹581 Cr increase
Remaining
₹0 Cr
Budget left
Budget Utilization
112.4%Spent
₹2764 Cr
Remaining
₹0 Cr
Total
₹2459 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1878 Cr
Revised Cost
₹2459 Cr
Increase
+₹581 Cr
Escalation
+30.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2024
Revised Completion
31/03/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹581 Cr (30.9%) from the original estimate of ₹1878 Cr.
Expenditure stands at ₹2764 Cr, which is 112.4% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Hotgi-Kudgi-Gadag Doubling Project is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1878.00 Cr, later revised to ₹2459.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Hotgi-Kudgi-Gadag Doubling Project"?
- Hotgi-Kudgi-Gadag Doubling Project is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹1878 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1878 Cr and has been revised to ₹2459 Cr — a cost overrun of +30.9%. Expenditure to date: ₹2764 Cr (112.4% of revised cost). Data as of 2026-02.
- QWhich ministry is responsible for this project?
- Hotgi-Kudgi-Gadag Doubling Project is under the Ministry of Railways in the Railways sector. Project code: 705662. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Hotgi-Kudgi-Gadag Doubling Project is one of several Bihar projects tracked under the Railways sector on the IPM system.