Original Cost
₹744 Cr
Baseline estimate
Revised Cost
₹1123 Cr
Latest approved cost
Expenditure
₹1161 Cr
Spent to date
Utilization
103.5%
Of revised budget
Cost Status
+50.9%
+₹379 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹1161 Cr
Remaining
₹0 Cr
Total
₹1123 Cr
Original Cost
₹744 Cr
Revised Cost
₹1123 Cr
Increase
+₹379 Cr
Escalation
+50.9%
Project Approved
Construction / Implementation
Original End Date
31/03/2023
Revised Completion
30/06/2026
Completed
Cost has increased by ₹379 Cr (50.9%) from the original estimate of ₹744 Cr.
Expenditure stands at ₹1161 Cr, which is 103.5% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.