Original Cost
₹1022 Cr
Baseline estimate
Revised Cost
₹1091 Cr
Latest approved cost
Expenditure
₹699 Cr
Spent to date
Utilization
64.0%
Of revised budget
Cost Status
+6.8%
+₹69 Cr increase
Remaining
₹393 Cr
Budget left
Spent
₹699 Cr
Remaining
₹393 Cr
Total
₹1091 Cr
Original Cost
₹1022 Cr
Revised Cost
₹1091 Cr
Increase
+₹69 Cr
Escalation
+6.8%
Project Approved
Construction / Implementation
Original End Date
07/03/2019
Revised Completion
30/06/2026
Completed
Cost has increased by ₹69 Cr (6.8%) from the original estimate of ₹1022 Cr.
Expenditure stands at ₹699 Cr, which is 64.0% of the revised project cost.
Remaining budget: ₹393 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.