to km 57.049 of NH-98
Original Cost
₹1126 Cr
Baseline estimate
Revised Cost
₹1187 Cr
Latest approved cost
Expenditure
₹610 Cr
Spent to date
Utilization
51.4%
Of revised cost
Cost Overrun
+5.4%
+₹61 Cr
Remaining
₹577 Cr
Budget left
Spent
₹610 Cr
Remaining
₹577 Cr
Total
₹1187 Cr
51.4%
Utilized
Original Cost
₹1126 Cr
Revised Cost
₹1187 Cr
Increase
+₹61 Cr
Escalation
+5.4%
Project Approved
Construction / Implementation
Original End Date
2024-02-29
Revised Completion
2026-06-30
Completed
Cost has increased by ₹61 Cr (5.4%) from the original estimate of ₹1126 Cr.
Expenditure stands at ₹610 Cr, which is 51.4% of the revised project cost.
Remaining budget: ₹577 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.