Water ResourcesIPM · Central Project +75.7% overrun#400101

Gundlakamma project

Department of Water Resources, River Development & GRAndhra Pradesh
Revised Cost: ₹697 CrUtilization: 89.6%Overrun: +₹300 Cr

Original Cost

₹397 Cr

Baseline estimate

+76% overrun

Revised Cost

₹697 Cr

Latest approved cost

Expenditure

₹625 Cr

Spent to date

Utilization

89.6%

Of revised budget

Escalated

Cost Status

+75.7%

+₹300 Cr increase

Remaining

₹73 Cr

Budget left

Budget Utilization

89.6%
0%25%50%75%100%

Spent

₹625 Cr

Remaining

₹73 Cr

Total

₹697 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹397 Cr

Revised Cost

₹697 Cr

Increase

+₹300 Cr

Escalation

+75.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2019

Revised Completion

31/03/2027

Completed

Project Details

Project Code400101
SectorWater Resources
MinistryDepartment of Water Resources, River Development & GR
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹397 Cr
Revised Cost₹697 Cr
Expenditure₹625 Cr
Original End Date31/12/2019
Revised Date31/03/2027

Project Intelligence

Cost has increased by ₹300 Cr (75.7%) from the original estimate of ₹397 Cr.

Expenditure stands at ₹625 Cr, which is 89.6% of the revised project cost.

Remaining budget: ₹73 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.

Gundlakamma project is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹397.00 Cr, later revised to ₹697.39 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Gundlakamma project"?
Gundlakamma project is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Andhra Pradesh. Original cost: ₹397 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹397 Cr and has been revised to ₹697 Cr — a cost overrun of +75.7%. Expenditure to date: ₹625 Cr (89.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Gundlakamma project is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 400101. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Gundlakamma project is one of several Bihar projects tracked under the Water Resources sector on the IPM system.