Original Cost
₹667 Cr
Baseline estimate
Revised Cost
₹690 Cr
Latest approved cost
Expenditure
₹58 Cr
Spent to date
Utilization
8.4%
Of revised budget
Cost Status
+3.5%
+₹23 Cr increase
Remaining
₹633 Cr
Budget left
Spent
₹58 Cr
Remaining
₹633 Cr
Total
₹690 Cr
Original Cost
₹667 Cr
Revised Cost
₹690 Cr
Increase
+₹23 Cr
Escalation
+3.5%
Project Approved
Construction / Implementation
Original End Date
15/07/2027
Revised Completion
15/07/2027
Completed
Cost has increased by ₹23 Cr (3.5%) from the original estimate of ₹667 Cr.
Expenditure stands at ₹58 Cr, which is 8.4% of the revised project cost.
Remaining budget: ₹633 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.