Water ResourcesIPM · Central Project +77.5% overrun#701386

Gosikhurd Project

Department of Water Resources, River Development & GRMaharashtra
Revised Cost: ₹12.8K CrUtilization: 113.1%Overrun: +₹5574 Cr

Original Cost

₹7196 Cr

Baseline estimate

+78% overrun

Revised Cost

₹12.8K Cr

Latest approved cost

Expenditure

₹14.4K Cr

Spent to date

Utilization

113.1%

Of revised budget

Escalated

Cost Status

+77.5%

+₹5574 Cr increase

Remaining

₹0 Cr

Budget left

Budget Utilization

113.1%
0%25%50%75%100%

Spent

₹14.4K Cr

Remaining

₹0 Cr

Total

₹12.8K Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹7196 Cr

Revised Cost

₹12.8K Cr

Increase

+₹5574 Cr

Escalation

+77.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2019

Revised Completion

30/06/2028

Completed

Project Details

Project Code701386
SectorWater Resources
MinistryDepartment of Water Resources, River Development & GR
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹7196 Cr
Revised Cost₹12.8K Cr
Expenditure₹14.4K Cr
Original End Date31/12/2019
Revised Date30/06/2028

Project Intelligence

Mega infrastructure project worth ₹12.8K Cr — among the largest central projects in Maharashtra.

Cost has increased by ₹5574 Cr (77.5%) from the original estimate of ₹7196 Cr.

Expenditure stands at ₹14.4K Cr, which is 113.1% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.

Gosikhurd Project is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹7196.00 Cr, later revised to ₹12770.10 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Gosikhurd Project"?
Gosikhurd Project is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Maharashtra. Original cost: ₹7196 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹7196 Cr and has been revised to ₹12770 Cr — a cost overrun of +77.5%. Expenditure to date: ₹14440 Cr (113.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Gosikhurd Project is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 701386. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Gosikhurd Project is one of several Bihar projects tracked under the Water Resources sector on the IPM system.