project
Original Cost
₹1120 Cr
Baseline estimate
Revised Cost
₹1120 Cr
Latest approved cost
Expenditure
₹402 Cr
Spent to date
Utilization
35.9%
Of revised cost
Cost Overrun
On Budget
No escalation
Remaining
₹718 Cr
Budget left
Spent
₹402 Cr
Remaining
₹718 Cr
Total
₹1120 Cr
35.9%
Utilized
Project Approved
Construction / Implementation
Original End Date
2027-12-30
Revised Completion
Completed
Project is within original budget of ₹1120 Cr — no cost escalation recorded.
Expenditure stands at ₹402 Cr, which is 35.9% of the revised project cost.
Remaining budget: ₹718 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.