Original Cost
₹1171 Cr
Baseline estimate
Revised Cost
₹1171 Cr
Latest approved cost
Expenditure
₹421 Cr
Spent to date
Utilization
35.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹750 Cr
Budget left
Spent
₹421 Cr
Remaining
₹750 Cr
Total
₹1171 Cr
Project Approved
Construction / Implementation
Original End Date
28/02/2025
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹1171 Cr — no cost escalation recorded.
Expenditure stands at ₹421 Cr, which is 35.9% of the revised project cost.
Remaining budget: ₹750 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.