Four Laning of Una to Kodinar from km. 180.478 to km. 221.610 Package-V
Original Cost
₹878 Cr
Baseline estimate
Revised Cost
₹1127 Cr
Latest approved cost
Expenditure
₹1009 Cr
Spent to date
Utilization
89.5%
Of revised budget
Cost Status
+28.3%
+₹249 Cr increase
Remaining
₹118 Cr
Budget left
Budget Utilization
89.5%Spent
₹1009 Cr
Remaining
₹118 Cr
Total
₹1127 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹878 Cr
Revised Cost
₹1127 Cr
Increase
+₹249 Cr
Escalation
+28.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
08/08/2019
Revised Completion
31/03/2025
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹249 Cr (28.3%) from the original estimate of ₹878 Cr.
Expenditure stands at ₹1009 Cr, which is 89.5% of the revised project cost.
Remaining budget: ₹118 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Four Laning of Una to Kodinar from km. 180.478 to km. 221.610 Package-V is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹878.00 Cr, later revised to ₹1126.66 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Four Laning of Una to Kodinar from km. 180.478 to km. 221.610 Package-V"?
- Four Laning of Una to Kodinar from km. 180.478 to km. 221.610 Package-V is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹878 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹878 Cr and has been revised to ₹1127 Cr — a cost overrun of +28.3%. Expenditure to date: ₹1009 Cr (89.5% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Four Laning of Una to Kodinar from km. 180.478 to km. 221.61 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619145. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Four Laning of Una to Kodinar from km. 180.478 to km. 221.61 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.