Original Cost
₹878 Cr
Baseline estimate
Revised Cost
₹1127 Cr
Latest approved cost
Expenditure
₹631 Cr
Spent to date
Utilization
56.0%
Of revised budget
Cost Status
+28.3%
+₹249 Cr increase
Remaining
₹496 Cr
Budget left
Spent
₹631 Cr
Remaining
₹496 Cr
Total
₹1127 Cr
Original Cost
₹878 Cr
Revised Cost
₹1127 Cr
Increase
+₹249 Cr
Escalation
+28.3%
Project Approved
Construction / Implementation
Original End Date
08/08/2019
Revised Completion
31/03/2025
Completed
Cost has increased by ₹249 Cr (28.3%) from the original estimate of ₹878 Cr.
Expenditure stands at ₹631 Cr, which is 56.0% of the revised project cost.
Remaining budget: ₹496 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.