Roads & HighwaysIPM · Central Project +4.9% overrun#619118

Four Laning of Angul to Sambalpur from Km.112.000 to Km.265.000

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹2633 CrUtilization: 93.6%Overrun: +₹123 Cr

Original Cost

₹2510 Cr

Baseline estimate

+5% overrun

Revised Cost

₹2633 Cr

Latest approved cost

Expenditure

₹2465 Cr

Spent to date

Utilization

93.6%

Of revised budget

Escalated

Cost Status

+4.9%

+₹123 Cr increase

Remaining

₹168 Cr

Budget left

Budget Utilization

93.6%
0%25%50%75%100%

Spent

₹2465 Cr

Remaining

₹168 Cr

Total

₹2633 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2510 Cr

Revised Cost

₹2633 Cr

Increase

+₹123 Cr

Escalation

+4.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/08/2019

Revised Completion

30/09/2026

Completed

Project Details

Project Code619118
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹2510 Cr
Revised Cost₹2633 Cr
Expenditure₹2465 Cr
Original End Date31/08/2019
Revised Date30/09/2026

Project Intelligence

Cost has increased by ₹123 Cr (4.9%) from the original estimate of ₹2510 Cr.

Expenditure stands at ₹2465 Cr, which is 93.6% of the revised project cost.

Remaining budget: ₹168 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Four Laning of Angul to Sambalpur from Km.112.000 to Km.265.000 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2510.00 Cr, later revised to ₹2632.91 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Four Laning of Angul to Sambalpur from Km.112.000 to Km.265.000"?
Four Laning of Angul to Sambalpur from Km.112.000 to Km.265.000 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹2510 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2510 Cr and has been revised to ₹2633 Cr — a cost overrun of +4.9%. Expenditure to date: ₹2465 Cr (93.6% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Four Laning of Angul to Sambalpur from Km.112.000 to Km.265. is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619118. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Four Laning of Angul to Sambalpur from Km.112.000 to Km.265. is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.