RailwaysIPM · Central Project +37.7% overrun#705639

Ernakulam-Kumbalam - Patch doubling 7.71 km

Ministry of RailwaysKerala
Revised Cost: ₹828 CrUtilization: 37.9%Overrun: +₹227 Cr

Original Cost

₹601 Cr

Baseline estimate

+38% overrun

Revised Cost

₹828 Cr

Latest approved cost

Expenditure

₹314 Cr

Spent to date

Utilization

37.9%

Of revised budget

Escalated

Cost Status

+37.7%

+₹227 Cr increase

Remaining

₹514 Cr

Budget left

Budget Utilization

37.9%
0%25%50%75%100%

Spent

₹314 Cr

Remaining

₹514 Cr

Total

₹828 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹601 Cr

Revised Cost

₹828 Cr

Increase

+₹227 Cr

Escalation

+37.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2028

Revised Completion

28/02/2027

Completed

Project Details

Project Code705639
SectorRailways
MinistryMinistry of Railways
StateKerala
Data Month2026-08

Financial Summary

Original Cost₹601 Cr
Revised Cost₹828 Cr
Expenditure₹314 Cr
Original End Date31/03/2028
Revised Date28/02/2027

Project Intelligence

Cost has increased by ₹227 Cr (37.7%) from the original estimate of ₹601 Cr.

Expenditure stands at ₹314 Cr, which is 37.9% of the revised project cost.

Remaining budget: ₹514 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Ernakulam-Kumbalam - Patch doubling 7.71 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹601.00 Cr, later revised to ₹827.50 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Ernakulam-Kumbalam - Patch doubling 7.71 km"?
Ernakulam-Kumbalam - Patch doubling 7.71 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Kerala. Original cost: ₹601 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹601 Cr and has been revised to ₹828 Cr — a cost overrun of +37.7%. Expenditure to date: ₹314 Cr (37.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Ernakulam-Kumbalam - Patch doubling 7.71 km is under the Ministry of Railways in the Railways sector. Project code: 705639. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Ernakulam-Kumbalam - Patch doubling 7.71 km is one of several Bihar projects tracked under the Railways sector on the IPM system.