Roads & HighwaysIPM · Central Project +3.2% overrun#618577

Dwarka Expressway Pkg-III Delhi/HR Border to Start of RoB Gurugram

Ministry of Road Transport & HighwaysHaryana
Revised Cost: ₹2298 CrUtilization: 76.6%Overrun: +₹70 Cr

Original Cost

₹2228 Cr

Baseline estimate

+3% overrun

Revised Cost

₹2298 Cr

Latest approved cost

Expenditure

₹1760 Cr

Spent to date

Utilization

76.6%

Of revised budget

Escalated

Cost Status

+3.2%

+₹70 Cr increase

Remaining

₹539 Cr

Budget left

Budget Utilization

76.6%
0%25%50%75%100%

Spent

₹1760 Cr

Remaining

₹539 Cr

Total

₹2298 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹2228 Cr

Revised Cost

₹2298 Cr

Increase

+₹70 Cr

Escalation

+3.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

27/11/2020

Revised Completion

31/05/2024

Completed

Project Details

Project Code618577
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateHaryana
Data Month2026-06

Financial Summary

Original Cost₹2228 Cr
Revised Cost₹2298 Cr
Expenditure₹1760 Cr
Original End Date27/11/2020
Revised Date31/05/2024

Project Intelligence

Cost has increased by ₹70 Cr (3.2%) from the original estimate of ₹2228 Cr.

Expenditure stands at ₹1760 Cr, which is 76.6% of the revised project cost.

Remaining budget: ₹539 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Dwarka Expressway Pkg-III Delhi/HR Border to Start of RoB Gurugram is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹2228.00 Cr, later revised to ₹2298.37 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Dwarka Expressway Pkg-III Delhi/HR Border to Start of RoB Gurugram"?
Dwarka Expressway Pkg-III Delhi/HR Border to Start of RoB Gurugram is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Haryana. Original cost: ₹2228 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹2228 Cr and has been revised to ₹2298 Cr — a cost overrun of +3.2%. Expenditure to date: ₹1760 Cr (76.6% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Dwarka Expressway Pkg-III Delhi/HR Border to Start of RoB Gu is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618577. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Dwarka Expressway Pkg-III Delhi/HR Border to Start of RoB Gu is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.