Project
Original Cost
₹691 Cr
Baseline estimate
Revised Cost
₹972 Cr
Latest approved cost
Expenditure
₹979 Cr
Spent to date
Utilization
100.7%
Of revised cost
Cost Overrun
+40.7%
+₹281 Cr
Remaining
₹0 Cr
Budget left
Spent
₹979 Cr
Remaining
₹0 Cr
Total
₹972 Cr
100.7%
Utilized
Original Cost
₹691 Cr
Revised Cost
₹972 Cr
Increase
+₹281 Cr
Escalation
+40.7%
Project Approved
Construction / Implementation
Original End Date
2019-12-31
Revised Completion
2024-12-31
Completed
Cost has increased by ₹281 Cr (40.7%) from the original estimate of ₹691 Cr.
Expenditure stands at ₹979 Cr, which is 100.7% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.