RailwaysIPM · Central Project#617215

Doubling between Parbhani-Parli Vaijnath stations 64.71 km PB34/CR/2023-24

Ministry of RailwaysMaharashtra
Revised Cost: ₹770 CrUtilization: 23.2%

Original Cost

₹770 Cr

Baseline estimate

On budget

Revised Cost

₹770 Cr

Latest approved cost

Expenditure

₹179 Cr

Spent to date

Utilization

23.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹592 Cr

Budget left

Budget Utilization

23.2%
0%25%50%75%100%

Spent

₹179 Cr

Remaining

₹592 Cr

Total

₹770 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2028

Revised Completion

Completed

Project Details

Project Code617215
SectorRailways
MinistryMinistry of Railways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹770 Cr
Revised Cost₹770 Cr
Expenditure₹179 Cr
Original End Date31/03/2028
Revised DateN/A

Project Intelligence

Project is within original budget of ₹770 Cr — no cost escalation recorded.

Expenditure stands at ₹179 Cr, which is 23.2% of the revised project cost.

Remaining budget: ₹592 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Doubling between Parbhani-Parli Vaijnath stations 64.71 km PB34/CR/2023-24 is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹770.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Doubling between Parbhani-Parli Vaijnath stations 64.71 km PB34/CR/2023-24"?
Doubling between Parbhani-Parli Vaijnath stations 64.71 km PB34/CR/2023-24 is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹770 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹770 Cr has not been significantly revised. Expenditure: ₹179 Cr (23.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Doubling between Parbhani-Parli Vaijnath stations 64.71 km P is under the Ministry of Railways in the Railways sector. Project code: 617215. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Doubling between Parbhani-Parli Vaijnath stations 64.71 km P is one of several Bihar projects tracked under the Railways sector on the IPM system.