Original Cost
₹351 Cr
Baseline estimate
Revised Cost
₹521 Cr
Latest approved cost
Expenditure
₹500 Cr
Spent to date
Utilization
95.8%
Of revised budget
Cost Status
+48.6%
+₹170 Cr increase
Remaining
₹22 Cr
Budget left
Spent
₹500 Cr
Remaining
₹22 Cr
Total
₹521 Cr
Original Cost
₹351 Cr
Revised Cost
₹521 Cr
Increase
+₹170 Cr
Escalation
+48.6%
Project Approved
Construction / Implementation
Original End Date
01/02/2025
Revised Completion
30/09/2025
Completed
Cost has increased by ₹170 Cr (48.6%) from the original estimate of ₹351 Cr.
Expenditure stands at ₹500 Cr, which is 95.8% of the revised project cost.
Remaining budget: ₹22 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.