Roads & HighwaysIPM · Central Project#618155

Development/Widening of Talegaon Chakan Shikrapur Nhavara Section of NH-548D from existing chainage km. 54/000 to 82/300 and Design chainage Km. 54/000 to 82/120 Shikrapur to Nhavara Section to 2LPS/4L Configuration on EPC Mode in the State of Maharashtra.

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹396 CrUtilization: 60.0%

Original Cost

₹396 Cr

Baseline estimate

On budget

Revised Cost

₹396 Cr

Latest approved cost

Expenditure

₹238 Cr

Spent to date

Utilization

60.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹158 Cr

Budget left

Budget Utilization

60.0%
0%25%50%75%100%

Spent

₹238 Cr

Remaining

₹158 Cr

Total

₹396 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

09/07/2026

Revised Completion

31/03/2027

Completed

Project Details

Project Code618155
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹396 Cr
Revised Cost₹396 Cr
Expenditure₹238 Cr
Original End Date09/07/2026
Revised Date31/03/2027

Project Intelligence

Project is within original budget of ₹396 Cr — no cost escalation recorded.

Expenditure stands at ₹238 Cr, which is 60.0% of the revised project cost.

Remaining budget: ₹158 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Development/Widening of Talegaon Chakan Shikrapur Nhavara Section of NH-548D from existing chainage km. 54/000 to 82/300 and Design chainage Km. 54/000 to 82/120 Shikrapur to Nhavara Section to 2LPS/4L Configuration on EPC Mode in the State of Maharashtra. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹396.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Development/Widening of Talegaon Chakan Shikrapur Nhavara Section of NH-548D fro"?
Development/Widening of Talegaon Chakan Shikrapur Nhavara Section of NH-548D from existing chainage km. 54/000 to 82/300 and Design chainage Km. 54/000 to 82/120 Shikrapur to Nhavara Section to 2LPS/4L Configuration on EPC Mode in the State of Maharashtra. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹396 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹396 Cr has not been significantly revised. Expenditure: ₹238 Cr (60.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Development/Widening of Talegaon Chakan Shikrapur Nhavara Se is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618155. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Development/Widening of Talegaon Chakan Shikrapur Nhavara Se is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.