Original Cost
₹201 Cr
Baseline estimate
Revised Cost
₹198 Cr
Latest approved cost
Expenditure
₹57 Cr
Spent to date
Utilization
28.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹141 Cr
Budget left
Spent
₹57 Cr
Remaining
₹141 Cr
Total
₹198 Cr
Project Approved
Construction / Implementation
Original End Date
16/01/2026
Revised Completion
30/06/2027
Completed
Project is within original budget of ₹201 Cr — no cost escalation recorded.
Expenditure stands at ₹57 Cr, which is 28.8% of the revised project cost.
Remaining budget: ₹141 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.