Original Cost
₹683 Cr
Baseline estimate
Revised Cost
₹727 Cr
Latest approved cost
Expenditure
₹600 Cr
Spent to date
Utilization
82.5%
Of revised budget
Cost Status
+6.4%
+₹44 Cr increase
Remaining
₹127 Cr
Budget left
Spent
₹600 Cr
Remaining
₹127 Cr
Total
₹727 Cr
Original Cost
₹683 Cr
Revised Cost
₹727 Cr
Increase
+₹44 Cr
Escalation
+6.4%
Project Approved
Construction / Implementation
Original End Date
29/02/2020
Revised Completion
30/06/2026
Completed
Cost has increased by ₹44 Cr (6.4%) from the original estimate of ₹683 Cr.
Expenditure stands at ₹600 Cr, which is 82.5% of the revised project cost.
Remaining budget: ₹127 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Oil & Gas. Ministry: Ministry of Petroleum & Natural Gas.