Roads & HighwaysIPM · Central Project#618674

Development of 6L Sargi Basanwahi Section from km 42.800 to km 99.500 of NH-130CD Pkg-CG-2

Ministry of Road Transport & HighwaysChhattisgarh
Revised Cost: ₹1462 CrUtilization: 51.8%

Original Cost

₹1471 Cr

Baseline estimate

On budget

Revised Cost

₹1462 Cr

Latest approved cost

Expenditure

₹758 Cr

Spent to date

Utilization

51.8%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹704 Cr

Budget left

Budget Utilization

51.8%
0%25%50%75%100%

Spent

₹758 Cr

Remaining

₹704 Cr

Total

₹1462 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

08/01/2025

Revised Completion

31/10/2026

Completed

Project Details

Project Code618674
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateChhattisgarh
Data Month2026-08

Financial Summary

Original Cost₹1471 Cr
Revised Cost₹1462 Cr
Expenditure₹758 Cr
Original End Date08/01/2025
Revised Date31/10/2026

Project Intelligence

Project is within original budget of ₹1471 Cr — no cost escalation recorded.

Expenditure stands at ₹758 Cr, which is 51.8% of the revised project cost.

Remaining budget: ₹704 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Development of 6L Sargi Basanwahi Section from km 42.800 to km 99.500 of NH-130CD Pkg-CG-2 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1471.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Development of 6L Sargi Basanwahi Section from km 42.800 to km 99.500 of NH-130"?
Development of 6L Sargi Basanwahi Section from km 42.800 to km 99.500 of NH-130CD Pkg-CG-2 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Chhattisgarh. Original cost: ₹1471 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1471 Cr and has been revised to ₹1462 Cr — a cost overrun of -0.6%. Expenditure to date: ₹758 Cr (51.8% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Development of 6L Sargi Basanwahi Section from km 42.800 to is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618674. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Development of 6L Sargi Basanwahi Section from km 42.800 to is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.