Original Cost
₹1755 Cr
Baseline estimate
Revised Cost
₹2167 Cr
Latest approved cost
Expenditure
₹885 Cr
Spent to date
Utilization
40.8%
Of revised budget
Cost Status
+23.5%
+₹412 Cr increase
Remaining
₹1283 Cr
Budget left
Spent
₹885 Cr
Remaining
₹1283 Cr
Total
₹2167 Cr
Original Cost
₹1755 Cr
Revised Cost
₹2167 Cr
Increase
+₹412 Cr
Escalation
+23.5%
Project Approved
Construction / Implementation
Original End Date
14/01/2025
Revised Completion
30/06/2027
Completed
Cost has increased by ₹412 Cr (23.5%) from the original estimate of ₹1755 Cr.
Expenditure stands at ₹885 Cr, which is 40.8% of the revised project cost.
Remaining budget: ₹1283 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.