Original Cost
₹646 Cr
Baseline estimate
Revised Cost
₹750 Cr
Latest approved cost
Expenditure
₹604 Cr
Spent to date
Utilization
80.6%
Of revised budget
Cost Status
+16.1%
+₹104 Cr increase
Remaining
₹146 Cr
Budget left
Spent
₹604 Cr
Remaining
₹146 Cr
Total
₹750 Cr
Original Cost
₹646 Cr
Revised Cost
₹750 Cr
Increase
+₹104 Cr
Escalation
+16.1%
Project Approved
Construction / Implementation
Original End Date
15/08/2025
Revised Completion
30/11/2026
Completed
Cost has increased by ₹104 Cr (16.1%) from the original estimate of ₹646 Cr.
Expenditure stands at ₹604 Cr, which is 80.6% of the revised project cost.
Remaining budget: ₹146 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.