Roads & HighwaysIPM · Central Project#619276

Development of 4-lane with paved shoulders from Budhel Junction to Vartej Y-Junction Km 0900 to Km 9400 on EPC mode under NHO in the State of Gujarat

Ministry of Road Transport & HighwaysGujarat
Revised Cost: ₹247 CrUtilization: 26.4%

Original Cost

₹247 Cr

Baseline estimate

On budget

Revised Cost

₹247 Cr

Latest approved cost

Expenditure

₹65 Cr

Spent to date

Utilization

26.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹182 Cr

Budget left

Budget Utilization

26.4%
0%25%50%75%100%

Spent

₹65 Cr

Remaining

₹182 Cr

Total

₹247 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

28/12/2027

Revised Completion

31/12/2026

Completed

Project Details

Project Code619276
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹247 Cr
Revised Cost₹247 Cr
Expenditure₹65 Cr
Original End Date28/12/2027
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹247 Cr — no cost escalation recorded.

Expenditure stands at ₹65 Cr, which is 26.4% of the revised project cost.

Remaining budget: ₹182 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Development of 4-lane with paved shoulders from Budhel Junction to Vartej Y-Junction Km 0900 to Km 9400 on EPC mode under NHO in the State of Gujarat is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹247.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Development of 4-lane with paved shoulders from Budhel Junction to Vartej Y-Junc"?
Development of 4-lane with paved shoulders from Budhel Junction to Vartej Y-Junction Km 0900 to Km 9400 on EPC mode under NHO in the State of Gujarat is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Gujarat. Original cost: ₹247 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹247 Cr has not been significantly revised. Expenditure: ₹65 Cr (26.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Development of 4-lane with paved shoulders from Budhel Junct is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619276. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Development of 4-lane with paved shoulders from Budhel Junct is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.