Original Cost
₹1186 Cr
Baseline estimate
Revised Cost
₹1259 Cr
Latest approved cost
Expenditure
₹1001 Cr
Spent to date
Utilization
79.5%
Of revised budget
Cost Status
+6.2%
+₹73 Cr increase
Remaining
₹259 Cr
Budget left
Spent
₹1001 Cr
Remaining
₹259 Cr
Total
₹1259 Cr
Original Cost
₹1186 Cr
Revised Cost
₹1259 Cr
Increase
+₹73 Cr
Escalation
+6.2%
Project Approved
Construction / Implementation
Original End Date
14/02/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹73 Cr (6.2%) from the original estimate of ₹1186 Cr.
Expenditure stands at ₹1001 Cr, which is 79.5% of the revised project cost.
Remaining budget: ₹259 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.