Original Cost
₹1555 Cr
Baseline estimate
Revised Cost
₹1556 Cr
Latest approved cost
Expenditure
₹1135 Cr
Spent to date
Utilization
72.9%
Of revised budget
Cost Status
+0.1%
+₹1 Cr increase
Remaining
₹421 Cr
Budget left
Spent
₹1135 Cr
Remaining
₹421 Cr
Total
₹1556 Cr
Original Cost
₹1555 Cr
Revised Cost
₹1556 Cr
Increase
+₹1 Cr
Escalation
+0.1%
Project Approved
Construction / Implementation
Original End Date
31/08/2024
Revised Completion
31/10/2026
Completed
Cost has increased by ₹1 Cr (0.1%) from the original estimate of ₹1555 Cr.
Expenditure stands at ₹1135 Cr, which is 72.9% of the revised project cost.
Remaining budget: ₹421 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.