Delhi Amritsar Katra Expressway Phase-II Pkg XVIII Development and Upgradation of Four lane Access Control Expressway from Design Chainage KM 530.00 to KM 545.300 Sidhra to Domel Section of NH-44
Original Cost
₹1026 Cr
Baseline estimate
Revised Cost
₹975 Cr
Latest approved cost
Expenditure
₹670 Cr
Spent to date
Utilization
68.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹305 Cr
Budget left
Budget Utilization
68.7%Spent
₹670 Cr
Remaining
₹305 Cr
Total
₹975 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
19/11/2025
Revised Completion
30/06/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1026 Cr — no cost escalation recorded.
Expenditure stands at ₹670 Cr, which is 68.7% of the revised project cost.
Remaining budget: ₹305 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Delhi Amritsar Katra Expressway Phase-II Pkg XVIII Development and Upgradation of Four lane Access Control Expressway from Design Chainage KM 530.00 to KM 545.300 Sidhra to Domel Section of NH-44 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1026.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Delhi Amritsar Katra Expressway Phase-II Pkg XVIII Development and Upgradation o"?
- Delhi Amritsar Katra Expressway Phase-II Pkg XVIII Development and Upgradation of Four lane Access Control Expressway from Design Chainage KM 530.00 to KM 545.300 Sidhra to Domel Section of NH-44 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹1026 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1026 Cr and has been revised to ₹975 Cr — a cost overrun of -4.9%. Expenditure to date: ₹670 Cr (68.7% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Delhi Amritsar Katra Expressway Phase-II Pkg XVIII Developme is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618497. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi Amritsar Katra Expressway Phase-II Pkg XVIII Developme is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.