Delhi-Amritsar-Katra Expressway Phase-II Pkg-XVI Existing Jakh Vijaypur-Kunjwani section of NH-44 including spur Connectivity to Jammu Airport NH-144A [Km 503500 to km 514500]
Original Cost
₹1822 Cr
Baseline estimate
Revised Cost
₹2523 Cr
Latest approved cost
Expenditure
₹1243 Cr
Spent to date
Utilization
49.3%
Of revised budget
Cost Status
+38.5%
+₹701 Cr increase
Remaining
₹1280 Cr
Budget left
Budget Utilization
49.3%Spent
₹1243 Cr
Remaining
₹1280 Cr
Total
₹2523 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1822 Cr
Revised Cost
₹2523 Cr
Increase
+₹701 Cr
Escalation
+38.5%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
26/09/2024
Revised Completion
30/09/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹701 Cr (38.5%) from the original estimate of ₹1822 Cr.
Expenditure stands at ₹1243 Cr, which is 49.3% of the revised project cost.
Remaining budget: ₹1280 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Delhi-Amritsar-Katra Expressway Phase-II Pkg-XVI Existing Jakh Vijaypur-Kunjwani section of NH-44 including spur Connectivity to Jammu Airport NH-144A [Km 503500 to km 514500] is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1822.00 Cr, later revised to ₹2522.56 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Delhi-Amritsar-Katra Expressway Phase-II Pkg-XVI Existing Jakh Vijaypur-Kunjwani"?
- Delhi-Amritsar-Katra Expressway Phase-II Pkg-XVI Existing Jakh Vijaypur-Kunjwani section of NH-44 including spur Connectivity to Jammu Airport NH-144A [Km 503500 to km 514500] is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹1822 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1822 Cr and has been revised to ₹2523 Cr — a cost overrun of +38.5%. Expenditure to date: ₹1243 Cr (49.3% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Delhi-Amritsar-Katra Expressway Phase-II Pkg-XVI Existing Ja is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618496. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi-Amritsar-Katra Expressway Phase-II Pkg-XVI Existing Ja is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.