Original Cost
₹1822 Cr
Baseline estimate
Revised Cost
₹2523 Cr
Latest approved cost
Expenditure
₹1171 Cr
Spent to date
Utilization
46.4%
Of revised budget
Cost Status
+38.5%
+₹701 Cr increase
Remaining
₹1351 Cr
Budget left
Spent
₹1171 Cr
Remaining
₹1351 Cr
Total
₹2523 Cr
Original Cost
₹1822 Cr
Revised Cost
₹2523 Cr
Increase
+₹701 Cr
Escalation
+38.5%
Project Approved
Construction / Implementation
Original End Date
26/09/2024
Revised Completion
30/09/2026
Completed
Cost has increased by ₹701 Cr (38.5%) from the original estimate of ₹1822 Cr.
Expenditure stands at ₹1171 Cr, which is 46.4% of the revised project cost.
Remaining budget: ₹1351 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.