Original Cost
₹1760 Cr
Baseline estimate
Revised Cost
₹1774 Cr
Latest approved cost
Expenditure
₹1250 Cr
Spent to date
Utilization
70.5%
Of revised budget
Cost Status
+0.8%
+₹14 Cr increase
Remaining
₹524 Cr
Budget left
Spent
₹1250 Cr
Remaining
₹524 Cr
Total
₹1774 Cr
Original Cost
₹1760 Cr
Revised Cost
₹1774 Cr
Increase
+₹14 Cr
Escalation
+0.8%
Project Approved
Construction / Implementation
Original End Date
09/07/2024
Revised Completion
30/06/2026
Completed
Cost has increased by ₹14 Cr (0.8%) from the original estimate of ₹1760 Cr.
Expenditure stands at ₹1250 Cr, which is 70.5% of the revised project cost.
Remaining budget: ₹524 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.