Original Cost
₹1866 Cr
Baseline estimate
Revised Cost
₹2430 Cr
Latest approved cost
Expenditure
₹1082 Cr
Spent to date
Utilization
44.5%
Of revised budget
Cost Status
+30.2%
+₹564 Cr increase
Remaining
₹1348 Cr
Budget left
Spent
₹1082 Cr
Remaining
₹1348 Cr
Total
₹2430 Cr
Original Cost
₹1866 Cr
Revised Cost
₹2430 Cr
Increase
+₹564 Cr
Escalation
+30.2%
Project Approved
Construction / Implementation
Original End Date
26/12/2023
Revised Completion
30/06/2026
Completed
Cost has increased by ₹564 Cr (30.2%) from the original estimate of ₹1866 Cr.
Expenditure stands at ₹1082 Cr, which is 44.5% of the revised project cost.
Remaining budget: ₹1348 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.