Delhi-Amritsar-Katra Expressway Phase-I Pkg-I from Jussur Kheri on NH-KMP Expressway to Junction with Rohtak-Panipat road NH-709 near Rukhi Paani village Km 0000 to Km 34000
Original Cost
₹1866 Cr
Baseline estimate
Revised Cost
₹2430 Cr
Latest approved cost
Expenditure
₹1610 Cr
Spent to date
Utilization
66.2%
Of revised budget
Cost Status
+30.2%
+₹564 Cr increase
Remaining
₹820 Cr
Budget left
Budget Utilization
66.2%Spent
₹1610 Cr
Remaining
₹820 Cr
Total
₹2430 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1866 Cr
Revised Cost
₹2430 Cr
Increase
+₹564 Cr
Escalation
+30.2%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
26/12/2023
Revised Completion
31/07/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹564 Cr (30.2%) from the original estimate of ₹1866 Cr.
Expenditure stands at ₹1610 Cr, which is 66.2% of the revised project cost.
Remaining budget: ₹820 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Delhi-Amritsar-Katra Expressway Phase-I Pkg-I from Jussur Kheri on NH-KMP Expressway to Junction with Rohtak-Panipat road NH-709 near Rukhi Paani village Km 0000 to Km 34000 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹1866.00 Cr, later revised to ₹2429.90 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Delhi-Amritsar-Katra Expressway Phase-I Pkg-I from Jussur Kheri on NH-KMP Expres"?
- Delhi-Amritsar-Katra Expressway Phase-I Pkg-I from Jussur Kheri on NH-KMP Expressway to Junction with Rohtak-Panipat road NH-709 near Rukhi Paani village Km 0000 to Km 34000 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Haryana. Original cost: ₹1866 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1866 Cr and has been revised to ₹2430 Cr — a cost overrun of +30.2%. Expenditure to date: ₹1610 Cr (66.2% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Delhi-Amritsar-Katra Expressway Phase-I Pkg-I from Jussur Kh is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618482. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Delhi-Amritsar-Katra Expressway Phase-I Pkg-I from Jussur Kh is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.