Daund - Manmad 247.50 km
Original Cost
₹2081 Cr
Baseline estimate
Revised Cost
₹3555 Cr
Latest approved cost
Expenditure
₹3271 Cr
Spent to date
Utilization
92.0%
Of revised budget
Cost Status
+70.8%
+₹1474 Cr increase
Remaining
₹284 Cr
Budget left
Budget Utilization
92.0%Spent
₹3271 Cr
Remaining
₹284 Cr
Total
₹3555 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹2081 Cr
Revised Cost
₹3555 Cr
Increase
+₹1474 Cr
Escalation
+70.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
01/12/2025
Revised Completion
31/03/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1474 Cr (70.8%) from the original estimate of ₹2081 Cr.
Expenditure stands at ₹3271 Cr, which is 92.0% of the revised project cost.
Remaining budget: ₹284 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Daund - Manmad 247.50 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹2081.00 Cr, later revised to ₹3554.74 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Daund - Manmad 247.50 km"?
- Daund - Manmad 247.50 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹2081 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹2081 Cr and has been revised to ₹3555 Cr — a cost overrun of +70.8%. Expenditure to date: ₹3271 Cr (92.0% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Daund - Manmad 247.50 km is under the Ministry of Railways in the Railways sector. Project code: 705504. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Daund - Manmad 247.50 km is one of several Bihar projects tracked under the Railways sector on the IPM system.