Original Cost
₹1628 Cr
Baseline estimate
Revised Cost
₹1628 Cr
Latest approved cost
Expenditure
₹1441 Cr
Spent to date
Utilization
88.5%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹187 Cr
Budget left
Spent
₹1441 Cr
Remaining
₹187 Cr
Total
₹1628 Cr
Project Approved
Construction / Implementation
Original End Date
30/09/2025
Revised Completion
31/12/2025
Completed
Project is within original budget of ₹1628 Cr — no cost escalation recorded.
Expenditure stands at ₹1441 Cr, which is 88.5% of the revised project cost.
Remaining budget: ₹187 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.