Original Cost
₹158 Cr
Baseline estimate
Revised Cost
₹158 Cr
Latest approved cost
Expenditure
₹52 Cr
Spent to date
Utilization
32.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹106 Cr
Budget left
Spent
₹52 Cr
Remaining
₹106 Cr
Total
₹158 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
Completed
Project is within original budget of ₹158 Cr — no cost escalation recorded.
Expenditure stands at ₹52 Cr, which is 32.8% of the revised project cost.
Remaining budget: ₹106 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.