Original Cost
₹487 Cr
Baseline estimate
Revised Cost
₹487 Cr
Latest approved cost
Expenditure
₹223 Cr
Spent to date
Utilization
45.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹264 Cr
Budget left
Spent
₹223 Cr
Remaining
₹264 Cr
Total
₹487 Cr
Project Approved
Construction / Implementation
Original End Date
28/02/2025
Revised Completion
Completed
Project is within original budget of ₹487 Cr — no cost escalation recorded.
Expenditure stands at ₹223 Cr, which is 45.8% of the revised project cost.
Remaining budget: ₹264 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.