Cuttack-Angul Section of NH-42 New NH-55 from Km.60.200 to Km. 112.000 Pkg-II in the State of Odisha
Original Cost
₹991 Cr
Baseline estimate
Revised Cost
₹1169 Cr
Latest approved cost
Expenditure
₹1084 Cr
Spent to date
Utilization
92.8%
Of revised budget
Cost Status
+17.9%
+₹178 Cr increase
Remaining
₹84 Cr
Budget left
Budget Utilization
92.8%Spent
₹1084 Cr
Remaining
₹84 Cr
Total
₹1169 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹991 Cr
Revised Cost
₹1169 Cr
Increase
+₹178 Cr
Escalation
+17.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
06/09/2020
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹178 Cr (17.9%) from the original estimate of ₹991 Cr.
Expenditure stands at ₹1084 Cr, which is 92.8% of the revised project cost.
Remaining budget: ₹84 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Cuttack-Angul Section of NH-42 New NH-55 from Km.60.200 to Km. 112.000 Pkg-II in the State of Odisha is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹991.00 Cr, later revised to ₹1168.82 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Cuttack-Angul Section of NH-42 New NH-55 from Km.60.200 to Km. 112.000 Pkg-II in"?
- Cuttack-Angul Section of NH-42 New NH-55 from Km.60.200 to Km. 112.000 Pkg-II in the State of Odisha is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹991 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹991 Cr and has been revised to ₹1169 Cr — a cost overrun of +17.9%. Expenditure to date: ₹1084 Cr (92.8% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Cuttack-Angul Section of NH-42 New NH-55 from Km.60.200 to K is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619215. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Cuttack-Angul Section of NH-42 New NH-55 from Km.60.200 to K is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.