Original Cost
₹991 Cr
Baseline estimate
Revised Cost
₹1169 Cr
Latest approved cost
Expenditure
₹500 Cr
Spent to date
Utilization
42.8%
Of revised budget
Cost Status
+17.9%
+₹178 Cr increase
Remaining
₹669 Cr
Budget left
Spent
₹500 Cr
Remaining
₹669 Cr
Total
₹1169 Cr
Original Cost
₹991 Cr
Revised Cost
₹1169 Cr
Increase
+₹178 Cr
Escalation
+17.9%
Project Approved
Construction / Implementation
Original End Date
06/09/2020
Revised Completion
30/09/2026
Completed
Cost has increased by ₹178 Cr (17.9%) from the original estimate of ₹991 Cr.
Expenditure stands at ₹500 Cr, which is 42.8% of the revised project cost.
Remaining budget: ₹669 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.