Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km 60.200 Pkg-I in the State of Odisha
Original Cost
₹999 Cr
Baseline estimate
Revised Cost
₹1178 Cr
Latest approved cost
Expenditure
₹1133 Cr
Spent to date
Utilization
96.1%
Of revised budget
Cost Status
+17.9%
+₹179 Cr increase
Remaining
₹46 Cr
Budget left
Budget Utilization
96.1%Spent
₹1133 Cr
Remaining
₹46 Cr
Total
₹1178 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹999 Cr
Revised Cost
₹1178 Cr
Increase
+₹179 Cr
Escalation
+17.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
16/07/2020
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹179 Cr (17.9%) from the original estimate of ₹999 Cr.
Expenditure stands at ₹1133 Cr, which is 96.1% of the revised project cost.
Remaining budget: ₹46 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km 60.200 Pkg-I in the State of Odisha is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹999.00 Cr, later revised to ₹1178.31 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km 60.200 Pkg-I in the"?
- Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km 60.200 Pkg-I in the State of Odisha is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹999 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹999 Cr and has been revised to ₹1178 Cr — a cost overrun of +17.9%. Expenditure to date: ₹1133 Cr (96.1% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619119. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.