Original Cost
₹999 Cr
Baseline estimate
Revised Cost
₹1178 Cr
Latest approved cost
Expenditure
₹514 Cr
Spent to date
Utilization
43.6%
Of revised budget
Cost Status
+17.9%
+₹179 Cr increase
Remaining
₹665 Cr
Budget left
Spent
₹514 Cr
Remaining
₹665 Cr
Total
₹1178 Cr
Original Cost
₹999 Cr
Revised Cost
₹1178 Cr
Increase
+₹179 Cr
Escalation
+17.9%
Project Approved
Construction / Implementation
Original End Date
16/07/2020
Revised Completion
30/09/2026
Completed
Cost has increased by ₹179 Cr (17.9%) from the original estimate of ₹999 Cr.
Expenditure stands at ₹514 Cr, which is 43.6% of the revised project cost.
Remaining budget: ₹665 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.