Roads & HighwaysIPM · Central Project +17.9% overrun#619119

Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km 60.200 Pkg-I in the State of Odisha

Ministry of Road Transport & HighwaysOdisha
Revised Cost: ₹1178 CrUtilization: 96.1%Overrun: +₹179 Cr

Original Cost

₹999 Cr

Baseline estimate

+18% overrun

Revised Cost

₹1178 Cr

Latest approved cost

Expenditure

₹1133 Cr

Spent to date

Utilization

96.1%

Of revised budget

Escalated

Cost Status

+17.9%

+₹179 Cr increase

Remaining

₹46 Cr

Budget left

Budget Utilization

96.1%
0%25%50%75%100%

Spent

₹1133 Cr

Remaining

₹46 Cr

Total

₹1178 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹999 Cr

Revised Cost

₹1178 Cr

Increase

+₹179 Cr

Escalation

+17.9%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

16/07/2020

Revised Completion

31/12/2026

Completed

Project Details

Project Code619119
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹999 Cr
Revised Cost₹1178 Cr
Expenditure₹1133 Cr
Original End Date16/07/2020
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹179 Cr (17.9%) from the original estimate of ₹999 Cr.

Expenditure stands at ₹1133 Cr, which is 96.1% of the revised project cost.

Remaining budget: ₹46 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km 60.200 Pkg-I in the State of Odisha is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹999.00 Cr, later revised to ₹1178.31 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km 60.200 Pkg-I in the"?
Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km 60.200 Pkg-I in the State of Odisha is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹999 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹999 Cr and has been revised to ₹1178 Cr — a cost overrun of +17.9%. Expenditure to date: ₹1133 Cr (96.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619119. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.