Original Cost
₹512 Cr
Baseline estimate
Revised Cost
₹512 Cr
Latest approved cost
Expenditure
₹156 Cr
Spent to date
Utilization
30.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹356 Cr
Budget left
Spent
₹156 Cr
Remaining
₹356 Cr
Total
₹512 Cr
Project Approved
Construction / Implementation
Original End Date
24/02/2023
Revised Completion
31/10/2026
Completed
Project is within original budget of ₹512 Cr — no cost escalation recorded.
Expenditure stands at ₹156 Cr, which is 30.4% of the revised project cost.
Remaining budget: ₹356 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.