Original Cost
₹411 Cr
Baseline estimate
Revised Cost
₹411 Cr
Latest approved cost
Expenditure
₹169 Cr
Spent to date
Utilization
41.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹242 Cr
Budget left
Spent
₹169 Cr
Remaining
₹242 Cr
Total
₹411 Cr
Project Approved
Construction / Implementation
Original End Date
08/03/2026
Revised Completion
31/03/2027
Completed
Project is within original budget of ₹411 Cr — no cost escalation recorded.
Expenditure stands at ₹169 Cr, which is 41.1% of the revised project cost.
Remaining budget: ₹242 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.