Roads & HighwaysIPM · Central Project +201.1% overrun#618549

Construction of twin tube tunnels on Jammu Kashmir Ring Road NH-244A Between Design Ch. 50600 to 51700 and design Ch. 53535 to 55700 on EPC mode under residual NHDP component of Bharatmala Pariyojna

Ministry of Road Transport & HighwaysJammu & Kashmir
Revised Cost: ₹732 CrUtilization: 92.7%Overrun: +₹489 Cr

Original Cost

₹243 Cr

Baseline estimate

+201% overrun

Revised Cost

₹732 Cr

Latest approved cost

Expenditure

₹679 Cr

Spent to date

Utilization

92.7%

Of revised budget

Escalated

Cost Status

+201.1%

+₹489 Cr increase

Remaining

₹53 Cr

Budget left

Budget Utilization

92.7%
0%25%50%75%100%

Spent

₹679 Cr

Remaining

₹53 Cr

Total

₹732 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹243 Cr

Revised Cost

₹732 Cr

Increase

+₹489 Cr

Escalation

+201.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

07/06/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code618549
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹243 Cr
Revised Cost₹732 Cr
Expenditure₹679 Cr
Original End Date07/06/2025
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹489 Cr (201.1%) from the original estimate of ₹243 Cr.

Expenditure stands at ₹679 Cr, which is 92.7% of the revised project cost.

Remaining budget: ₹53 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of twin tube tunnels on Jammu Kashmir Ring Road NH-244A Between Design Ch. 50600 to 51700 and design Ch. 53535 to 55700 on EPC mode under residual NHDP component of Bharatmala Pariyojna is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹243.00 Cr, later revised to ₹731.59 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of twin tube tunnels on Jammu Kashmir Ring Road NH-244A Between Des"?
Construction of twin tube tunnels on Jammu Kashmir Ring Road NH-244A Between Design Ch. 50600 to 51700 and design Ch. 53535 to 55700 on EPC mode under residual NHDP component of Bharatmala Pariyojna is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Jammu & Kashmir. Original cost: ₹243 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹243 Cr and has been revised to ₹732 Cr — a cost overrun of +201.1%. Expenditure to date: ₹679 Cr (92.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of twin tube tunnels on Jammu Kashmir Ring Road is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618549. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of twin tube tunnels on Jammu Kashmir Ring Road is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.