Construction of Trumpet Interchange Connecting Bangalore Chennai Expressway km.261705 to km. 262800 with Maduravoyal to Walajapet Section of NH 48 near Sriperumbudur Toll Plaza at km. 35700
Original Cost
₹163 Cr
Baseline estimate
Revised Cost
₹163 Cr
Latest approved cost
Expenditure
₹60 Cr
Spent to date
Utilization
36.9%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹103 Cr
Budget left
Budget Utilization
36.9%Spent
₹60 Cr
Remaining
₹103 Cr
Total
₹163 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
23/08/2025
Revised Completion
31/10/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹163 Cr — no cost escalation recorded.
Expenditure stands at ₹60 Cr, which is 36.9% of the revised project cost.
Remaining budget: ₹103 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Trumpet Interchange Connecting Bangalore Chennai Expressway km.261705 to km. 262800 with Maduravoyal to Walajapet Section of NH 48 near Sriperumbudur Toll Plaza at km. 35700 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹163.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Trumpet Interchange Connecting Bangalore Chennai Expressway km."?
- Construction of Trumpet Interchange Connecting Bangalore Chennai Expressway km.261705 to km. 262800 with Maduravoyal to Walajapet Section of NH 48 near Sriperumbudur Toll Plaza at km. 35700 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Tamil Nadu. Original cost: ₹163 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹163 Cr and has been revised to ₹163 Cr — a cost overrun of -0.3%. Expenditure to date: ₹60 Cr (36.9% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Trumpet Interchange Connecting Bangalore Ch is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618480. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Trumpet Interchange Connecting Bangalore Ch is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.