Roads & HighwaysIPM · Central Project#618939

Construction of Standalone Flyover cum ROB from Design Ch.66.600 to Design Ch.68.800 in Gadchandur Town on NH-353B

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹108 CrUtilization: 37.1%

Original Cost

₹191 Cr

Baseline estimate

On budget

Revised Cost

₹108 Cr

Latest approved cost

Expenditure

₹40 Cr

Spent to date

Utilization

37.1%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹68 Cr

Budget left

Budget Utilization

37.1%
0%25%50%75%100%

Spent

₹40 Cr

Remaining

₹68 Cr

Total

₹108 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

25/07/2027

Revised Completion

25/07/2027

Completed

Project Details

Project Code618939
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹191 Cr
Revised Cost₹108 Cr
Expenditure₹40 Cr
Original End Date25/07/2027
Revised Date25/07/2027

Project Intelligence

Project is within original budget of ₹191 Cr — no cost escalation recorded.

Expenditure stands at ₹40 Cr, which is 37.1% of the revised project cost.

Remaining budget: ₹68 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Standalone Flyover cum ROB from Design Ch.66.600 to Design Ch.68.800 in Gadchandur Town on NH-353B is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹191.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Standalone Flyover cum ROB from Design Ch.66.600 to Design Ch.68"?
Construction of Standalone Flyover cum ROB from Design Ch.66.600 to Design Ch.68.800 in Gadchandur Town on NH-353B is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹191 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹191 Cr and has been revised to ₹108 Cr — a cost overrun of -43.6%. Expenditure to date: ₹40 Cr (37.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Standalone Flyover cum ROB from Design Ch.66 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618939. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Standalone Flyover cum ROB from Design Ch.66 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.