Original Cost
₹1052 Cr
Baseline estimate
Revised Cost
₹1117 Cr
Latest approved cost
Expenditure
₹653 Cr
Spent to date
Utilization
58.4%
Of revised budget
Cost Status
+6.2%
+₹65 Cr increase
Remaining
₹465 Cr
Budget left
Spent
₹653 Cr
Remaining
₹465 Cr
Total
₹1117 Cr
Original Cost
₹1052 Cr
Revised Cost
₹1117 Cr
Increase
+₹65 Cr
Escalation
+6.2%
Project Approved
Construction / Implementation
Original End Date
11/01/2026
Revised Completion
30/04/2026
Completed
Cost has increased by ₹65 Cr (6.2%) from the original estimate of ₹1052 Cr.
Expenditure stands at ₹653 Cr, which is 58.4% of the revised project cost.
Remaining budget: ₹465 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.