Roads & HighwaysIPM · Central Project#617931

Construction of ROB and its approaches in lieu of LC No. 10/B/T at Km 307.050 of NH-60.

Ministry of Road Transport & HighwaysWest Bengal
Revised Cost: ₹139 CrUtilization: 14.9%

Original Cost

₹156 Cr

Baseline estimate

On budget

Revised Cost

₹139 Cr

Latest approved cost

Expenditure

₹21 Cr

Spent to date

Utilization

14.9%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹118 Cr

Budget left

Budget Utilization

14.9%
0%25%50%75%100%

Spent

₹21 Cr

Remaining

₹118 Cr

Total

₹139 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

06/08/2025

Revised Completion

31/10/2027

Completed

Project Details

Project Code617931
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateWest Bengal
Data Month2026-08

Financial Summary

Original Cost₹156 Cr
Revised Cost₹139 Cr
Expenditure₹21 Cr
Original End Date06/08/2025
Revised Date31/10/2027

Project Intelligence

Project is within original budget of ₹156 Cr — no cost escalation recorded.

Expenditure stands at ₹21 Cr, which is 14.9% of the revised project cost.

Remaining budget: ₹118 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of ROB and its approaches in lieu of LC No. 10/B/T at Km 307.050 of NH-60. is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹156.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of ROB and its approaches in lieu of LC No. 10/B/T at Km 307.050 o"?
Construction of ROB and its approaches in lieu of LC No. 10/B/T at Km 307.050 of NH-60. is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: West Bengal. Original cost: ₹156 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹156 Cr and has been revised to ₹139 Cr — a cost overrun of -11.2%. Expenditure to date: ₹21 Cr (14.9% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of ROB and its approaches in lieu of LC No. 10 is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617931. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of ROB and its approaches in lieu of LC No. 10 is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.