Roads & HighwaysIPM · Central Project#617897

Construction of proposed 4Lane Revelgunj bypass NH-19 in the State of Bihar on EPC mode connecting NH 19 to 85 origin

Ministry of Road Transport & HighwaysBihar
Revised Cost: ₹295 CrUtilization: 60.5%

Original Cost

₹295 Cr

Baseline estimate

On budget

Revised Cost

₹295 Cr

Latest approved cost

Expenditure

₹179 Cr

Spent to date

Utilization

60.5%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹116 Cr

Budget left

Budget Utilization

60.5%
0%25%50%75%100%

Spent

₹179 Cr

Remaining

₹116 Cr

Total

₹295 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

09/07/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code617897
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateBihar
Data Month2026-08

Financial Summary

Original Cost₹295 Cr
Revised Cost₹295 Cr
Expenditure₹179 Cr
Original End Date09/07/2025
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹295 Cr — no cost escalation recorded.

Expenditure stands at ₹179 Cr, which is 60.5% of the revised project cost.

Remaining budget: ₹116 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of proposed 4Lane Revelgunj bypass NH-19 in the State of Bihar on EPC mode connecting NH 19 to 85 origin is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹295.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of proposed 4Lane Revelgunj bypass NH-19 in the State of Bihar on E"?
Construction of proposed 4Lane Revelgunj bypass NH-19 in the State of Bihar on EPC mode connecting NH 19 to 85 origin is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Bihar. Original cost: ₹295 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹295 Cr has not been significantly revised. Expenditure: ₹179 Cr (60.5% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of proposed 4Lane Revelgunj bypass NH-19 in the is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617897. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of proposed 4Lane Revelgunj bypass NH-19 in the is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.