Original Cost
₹179 Cr
Baseline estimate
Revised Cost
₹179 Cr
Latest approved cost
Expenditure
₹72 Cr
Spent to date
Utilization
40.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹107 Cr
Budget left
Spent
₹72 Cr
Remaining
₹107 Cr
Total
₹179 Cr
Project Approved
Construction / Implementation
Original End Date
19/12/2024
Revised Completion
Completed
Project is within original budget of ₹179 Cr — no cost escalation recorded.
Expenditure stands at ₹72 Cr, which is 40.1% of the revised project cost.
Remaining budget: ₹107 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.