Construction of Jharsuguda Bypass including Land acqusition on NH-49 from km 258.636 to km 283.300 design chainage 258.636 to km 289.876 under NHO in Annual Plan 2022-23 for the state of Odisha Job No.NH-49-OD-2022-23-655
Original Cost
₹587 Cr
Baseline estimate
Revised Cost
₹587 Cr
Latest approved cost
Expenditure
₹165 Cr
Spent to date
Utilization
28.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹422 Cr
Budget left
Budget Utilization
28.1%Spent
₹165 Cr
Remaining
₹422 Cr
Total
₹587 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
07/07/2027
Revised Completion
07/07/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹587 Cr — no cost escalation recorded.
Expenditure stands at ₹165 Cr, which is 28.1% of the revised project cost.
Remaining budget: ₹422 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Jharsuguda Bypass including Land acqusition on NH-49 from km 258.636 to km 283.300 design chainage 258.636 to km 289.876 under NHO in Annual Plan 2022-23 for the state of Odisha Job No.NH-49-OD-2022-23-655 is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹587.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Jharsuguda Bypass including Land acqusition on NH-49 from km 258"?
- Construction of Jharsuguda Bypass including Land acqusition on NH-49 from km 258.636 to km 283.300 design chainage 258.636 to km 289.876 under NHO in Annual Plan 2022-23 for the state of Odisha Job No.NH-49-OD-2022-23-655 is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Odisha. Original cost: ₹587 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹587 Cr has not been significantly revised. Expenditure: ₹165 Cr (28.1% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Jharsuguda Bypass including Land acqusition is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 617922. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Jharsuguda Bypass including Land acqusition is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.