Construction of Intermediate Lane Road with hard shoulder from design Km 0.000 to Km 17.387 Total length 17.387 km of Hunli to Ithun Bridge section on NH-913 Frontier Highway in State of Arunachal Pradesh on EPC mode under NHO-NE
Original Cost
₹276 Cr
Baseline estimate
Revised Cost
₹276 Cr
Latest approved cost
Expenditure
₹166 Cr
Spent to date
Utilization
60.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹110 Cr
Budget left
Budget Utilization
60.2%Spent
₹166 Cr
Remaining
₹110 Cr
Total
₹276 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/01/2027
Revised Completion
30/01/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹276 Cr — no cost escalation recorded.
Expenditure stands at ₹166 Cr, which is 60.2% of the revised project cost.
Remaining budget: ₹110 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.
Construction of Intermediate Lane Road with hard shoulder from design Km 0.000 to Km 17.387 Total length 17.387 km of Hunli to Ithun Bridge section on NH-913 Frontier Highway in State of Arunachal Pradesh on EPC mode under NHO-NE is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹276.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Construction of Intermediate Lane Road with hard shoulder from design Km 0.000 t"?
- Construction of Intermediate Lane Road with hard shoulder from design Km 0.000 to Km 17.387 Total length 17.387 km of Hunli to Ithun Bridge section on NH-913 Frontier Highway in State of Arunachal Pradesh on EPC mode under NHO-NE is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Arunachal Pradesh. Original cost: ₹276 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹276 Cr has not been significantly revised. Expenditure: ₹166 Cr (60.2% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Construction of Intermediate Lane Road with hard shoulder fr is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 618403. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Intermediate Lane Road with hard shoulder fr is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.