Original Cost
₹6809 Cr
Baseline estimate
Revised Cost
₹6809 Cr
Latest approved cost
Expenditure
₹3216 Cr
Spent to date
Utilization
47.2%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹3593 Cr
Budget left
Spent
₹3216 Cr
Remaining
₹3593 Cr
Total
₹6809 Cr
Project Approved
Construction / Implementation
Original End Date
30/09/2026
Revised Completion
28/02/2028
Completed
Project is within original budget of ₹6809 Cr — no cost escalation recorded.
Expenditure stands at ₹3216 Cr, which is 47.2% of the revised project cost.
Remaining budget: ₹3593 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.