Original Cost
₹2921 Cr
Baseline estimate
Revised Cost
₹3486 Cr
Latest approved cost
Expenditure
₹1089 Cr
Spent to date
Utilization
31.3%
Of revised budget
Cost Status
+19.3%
+₹565 Cr increase
Remaining
₹2396 Cr
Budget left
Spent
₹1089 Cr
Remaining
₹2396 Cr
Total
₹3486 Cr
Original Cost
₹2921 Cr
Revised Cost
₹3486 Cr
Increase
+₹565 Cr
Escalation
+19.3%
Project Approved
Construction / Implementation
Original End Date
21/06/2025
Revised Completion
16/04/2027
Completed
Cost has increased by ₹565 Cr (19.3%) from the original estimate of ₹2921 Cr.
Expenditure stands at ₹1089 Cr, which is 31.3% of the revised project cost.
Remaining budget: ₹2396 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.