and terminating at SH-74 near Manikpur 38814 at NH-139W under Bharatmalapariyona
Original Cost
₹1422 Cr
Baseline estimate
Revised Cost
₹1538 Cr
Latest approved cost
Expenditure
₹274 Cr
Spent to date
Utilization
17.8%
Of revised cost
Cost Overrun
+8.2%
+₹116 Cr
Remaining
₹1264 Cr
Budget left
Spent
₹274 Cr
Remaining
₹1264 Cr
Total
₹1538 Cr
17.8%
Utilized
Original Cost
₹1422 Cr
Revised Cost
₹1538 Cr
Increase
+₹116 Cr
Escalation
+8.2%
Project Approved
Construction / Implementation
Original End Date
2027-04-05
Revised Completion
2027-09-30
Completed
Cost has increased by ₹116 Cr (8.2%) from the original estimate of ₹1422 Cr.
Expenditure stands at ₹274 Cr, which is 17.8% of the revised project cost.
Remaining budget: ₹1264 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.