Roads & HighwaysIPM · Central Project#619300

Construction of Four Lane Nagpur-Katol section of NH-353J including Mitigation Structures from Design Ch. 37000 to Ch. 45990 Tiger Corridor-I Mitigation Structures from Design Ch. 37000 to Ch. 45990 Tiger Corridor-I in the State of Maharashtra on EPC Mode

Ministry of Road Transport & HighwaysMaharashtra
Revised Cost: ₹301 CrUtilization: 0.0%

Original Cost

₹301 Cr

Baseline estimate

On budget

Revised Cost

₹301 Cr

Latest approved cost

Expenditure

₹0 Cr

Spent to date

Utilization

0.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹301 Cr

Budget left

Budget Utilization

0.0%
0%25%50%75%100%

Spent

₹0 Cr

Remaining

₹301 Cr

Total

₹301 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

17/12/2027

Revised Completion

17/12/2027

Completed

Project Details

Project Code619300
SectorRoads & Highways
MinistryMinistry of Road Transport & Highways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹301 Cr
Revised Cost₹301 Cr
Expenditure₹0 Cr
Original End Date17/12/2027
Revised Date17/12/2027

Project Intelligence

Project is within original budget of ₹301 Cr — no cost escalation recorded.

Expenditure stands at ₹0 Cr, which is 0.0% of the revised project cost.

Remaining budget: ₹301 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Roads & Highways. Ministry: Ministry of Road Transport & Highways.

Construction of Four Lane Nagpur-Katol section of NH-353J including Mitigation Structures from Design Ch. 37000 to Ch. 45990 Tiger Corridor-I Mitigation Structures from Design Ch. 37000 to Ch. 45990 Tiger Corridor-I in the State of Maharashtra on EPC Mode is a centrally-funded infrastructure project under Ministry of Road Transport & Highways, in the Roads & Highways sector. The original approved cost is ₹301.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Construction of Four Lane Nagpur-Katol section of NH-353J including Mitigation S"?
Construction of Four Lane Nagpur-Katol section of NH-353J including Mitigation Structures from Design Ch. 37000 to Ch. 45990 Tiger Corridor-I Mitigation Structures from Design Ch. 37000 to Ch. 45990 Tiger Corridor-I in the State of Maharashtra on EPC Mode is a centrally-funded infrastructure project under the Ministry of Road Transport & Highways, tracked through the Investment Project Monitoring (IPM) system. Sector: Roads & Highways. State: Maharashtra. Original cost: ₹301 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹301 Cr has not been significantly revised. Expenditure: ₹0 Cr (N/A% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Construction of Four Lane Nagpur-Katol section of NH-353J in is under the Ministry of Road Transport & Highways in the Roads & Highways sector. Project code: 619300. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Construction of Four Lane Nagpur-Katol section of NH-353J in is one of several Bihar projects tracked under the Roads & Highways sector on the IPM system.